Problem:Earned-value analysis. A project budget calls for the following expenditures:TaskDateBudgeted

Problem:Earned-value analysis. A project budget calls for the following expenditures:TaskDateBudgeted AmountBuild formsApril 1$10,000Pour foundationApril 1$50,000May 1$100,000Frame wallsMay 1$30,000June 1$30,000Remaining tasksJuly 1 and beyond$500,000
Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  5. SV as of May 1.
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

Text

Title: Project Management  

Subtitle: https://opentextbc.ca/projectmanagement/ 

Authors: Adrienne Watt 

Publisher: BCcampus Open Education 

Publication Date: 2019 

Edition: 2nd Edition

Table of Contents

Calculate your order
Pages (275 words)
Standard price: $0.00

Latest Reviews

Impressed with the sample above? Wait there is more

Related Questions

Reflective paper

This paper needs to be in APA format. This paper should be a reflective paper about the opioid epidemic and should be about a patient

New questions

Don't Let Questions or Concerns Hold You Back - Make a Free Inquiry Now!